Bond Project List
Completed Bond Project List:
North Tahoe School and High School
- Cafeteria Modernization
- Vertical ADA Lifts
- New Stadium Bleachers
Kings Beach Elementary School Addition & Modernization
Construction Spring 2018 - Fall 2019
Tahoe Lake Elementary School Modernization & Addition
Phase 2: Construction June 2017 - August 2020
Truckee Elementary School Modernization & Addition
Construction May 2018 - October 2020
Alder Creek Middle School Parking Lot Expansion
Construction Completed in 2016
Cold Stream Alternative School
Construction Completed in 2015
District-Wide
Fire & Security System Upgrades at Select Sites Completed in 2015
Technology & Furniture Upgrades at Select Sites Completed in 2015
Donner Trail Elementary School Modernization & Addition
Construction Completed 2018
Glenshire Elementary School
Phase 1 Completed in 2015 - Included Parking Lot Upgrade, Classroom Modifications, Safety & Security Upgrades
Phase 2 Completed in 2016
Maintenance & Operations Warehouse
Construction Completed in 2017
North Tahoe High School
A portion of Bus Barn Converted Into Storage Space Completed in 2015
Sierra Continuation High School
Construction Completed in 2019
Sierra Expeditionary Learning School Parking Lot & FF&E
Phase 1 Construction Completed in 2015
Phase 2 Construction Completed in 2016
Tahoe Lake Elementary School Modernization & Addition 2017-2020
Boiler Replacement & Controls Upgrade Completed in 2015
Phase 1 Parking lot Expansion Completed in 2016
Truckee High School Modernization & Addition
- Track & Field Upgrade Completed in 2017
- Phase 1 New Track & Field: Construction Completed in 2016
- Phase 2 Increment 1: West Wing - Completed Aug 2018
- Phase 2 Increment 2: East Wing - Construction Jun 2019 - Dec 2020